Semiconductor supply chain bottlenecks spread from wafers all the way upstream to carrier boards and manufacturing equipment. Korean media ETNews According to reports, the delivery time for some equipment used to produce flip-chip ball grid array packaging (FC-BGA) carrier boards has been extended five times from about 6 months to about 30 months after ordering. In order to grab orders from major AI chip manufacturers, major carrier board manufacturers such as Japan's Ibiden, Shinko Electric Industries, South Korea's Samsung Electro-Mechanics and Taiwan's Xinxing (3037) are accelerating their production expansion.

The delivery time of carrier board equipment has been extended five times: operators submit letters of intent, pay in advance and rush for goods

The report pointed out that the delivery time of some FC-BGA carrier board production equipment has been extended from about 6 months to about 30 months after the order is placed. In order to obtain equipment before their competitors, some carrier board manufacturers submit letters of intent to equipment vendors before formally placing purchase orders; some also pay advance payments in the hope of speeding up delivery. However, even at this level, the delivery time is still quite long, and only a few manufacturers can get supply commitments.

This phenomenon of grabbing equipment can also be seen in Taiwanese factories. Xinxing announced on October 27 that its board of directors decided to increase the amount of long-delivery equipment purchase orders by approximately NT$50.9 billion. This is the fourth time this year that Xinxing has increased the amount of pre-orders for long-delivery equipment, and it is also the largest single amount.

(Carrier board factory Xinxing's pre-orders for long-delivery equipment increased by another 50.9 billion yuan, the fourth increase this year)

Japan's precision components are out of stock, which is the key to extending equipment delivery time

Reports believe that the shortage of components in Japan is the main reason for the long equipment delivery time. Advanced manufacturing equipment relies heavily on Japanese precision motors, drive components, servo motors and controllers, but these suppliers have limited production capacity. An FC-BGA bonding equipment manufacturer said that Japanese components that used to be readily available now take about six months to arrive.

Huida and Tesla have directly stepped down to tie up their production capacity, while Japan, South Korea and Taiwan are stuck in their respective positions.

AI chip developers have also shifted from passively waiting for supply to proactively stepping in to lock in carrier board production capacity. 《daily economic news》Previously reported that NVIDIA plans to cooperate with Samsung Electro-Mechanics, Ifiden and Xinxing through investment and supply arrangements to increase the substrate production capacity of its products to 2.5 times the current level in the next three years. This also echoes what Huida announced at the GTC conference in Berlin in October.Production expansion plan with six supply chain partners. The progress of the three carrier board factories is different:

  • Japan's Ibiden: Huida has provided billions of dollars in advance payments for production capacity to support the expansion of local factories, with the goal of increasing production capacity to three times the current level. The new production capacity is expected to be ramped up in the first quarter of 2028.
  • South Korea's Samsung Electro-Mechanics: Newly added to Huida's carrier board supply chain, it will first supply products from existing production lines in South Korea and build new factories in Sejong and Busan.
  • Taiwan Xinxing: Signed a capacity reservation agreement with Huida to expand Taiwan's carrier board production line. It is expected to start increasing production capacity in the second quarter of 2027 and reach full capacity in mid-2028.

In the Taiwanese factory camp, Huida recently joined Jingshuo as a new partner.Chain News Report, Jingshuo's ABF carrier board production capacity exclusively for Huida will be expanded to more than 3.5 times the existing capacity. The new production capacity will come from the Taoyuan Young Lion factory and is expected to start production in the second half of 2027.

Tesla has adopted a similar strategy, reportedly pledging to invest 1.1 trillion won to support Samsung Electro-Mechanics' Sejong expansion project in exchange for a guaranteed supply of FC-BGA from 2029 to 2033 for the AI ​​chips required for self-driving cars and Optimus robots.

Samsung Electro-Mechanics spent 6.78 trillion won to expand production, but demand still exceeds supply

Despite aggressive production expansion plans, the supply of high-end carrier boards remains tight. according to"Korea JoongAng Ilbo” reported that Samsung Electro-Mechanics announced in September that it would invest a total of 6.78 trillion won (approximately US$5 billion) to expand FC-BGA production capacity in South Korea and Vietnam. About 4.3 trillion won will be invested in Sejong, aiming for mass production in September 2028; approximately 2.5 trillion won will be invested in Vietnam, and the new factory is expected to start operation in June 2030.

Even so, Samsung Electro-Mechanics still expects that production capacity will not be enough to meet total customer demand and is considering further additional investment.

The shortage of carrier boards may extend beyond 2028

Judging from the intersection of delivery time and production expansion schedule, this round of carrier board shortage is difficult to alleviate in the short term. Based on a 30-month delivery period, this type of equipment ordered in November 2026 will not be delivered until mid-2029 at the earliest; for companies still scrambling for equipment, when the equipment and Japanese components will arrive will become the biggest variable in whether production expansion can be ramped up as scheduled.

As the AI ​​material shortage bottleneck is changing frommemory steering carrier board, ABF carrier board priceGain up to 15% quarterly. With customers such as Huida and Tesla using prepayments and long-term contracts to bind production capacity, whether Taiwan's carrier board manufacturers can maintain progress before the equipment is in place will be the focus of observation.

this article The delivery time of the carrier board equipment is 30 months! Huida and Tesla are on the firing line, with Japanese, Korean and Taiwanese factories taking the lead. first appeared in Chain News ABMedia。